Configure the actual costing per week
Before you can use the Actual costing per week function, you first have to configure this functionality.
Description
Note:
If you use this functionality, the actual costing lines present in Actual costing per line are not taken into account. This is also the case when you start using both functions.
Procedure
- Activate Actual costing per week
Before you can use the Actual costing per week function, you first have to activate this functionality.
- Add a weekly period table
You have to create a new periodic table for Actual costing per week.
- Link a weekly table in the projects' settings
After you have added a weekly table, you also have to link this table in the project settings.
- Adjust an entry layout for Actual costing per week
Profit comes with a default entry layout for entering the hours per week. You can also add your own entry layout.