Set up project for displaying actual costing in Profit Calendar

Configure each product where Profit has to integrate the actual costing and display it in Profit Calendar.

Set up project for displaying actual costing in Profit Calendar:

  1. Go to: Projects / Project / Project.
  2. Open the project properties.
  3. Go to the tab: General.
  4. Select the Actual costing to calendar check box.
  5. Click on: OK
  6. Repeat this for each project where you want the actual costing lines to be displayed in the employee/user's Profit Calendar.