Use teams in a cost estimate
If you have configured it in the entry layout of the cost estimate, you can create a team from your employees in the cost estimate. The team that you add from the cost estimate is always a specific team, never a generic one.
Creating a team in the cost estimate is also possible if you use the setting Quotation number same as project number for the numbering of the cost estimate.
If you change the cost estimate, Profit only adds new team members to the associated team.
To use teams in a cost estimate:
- Go to: Projects / Cost estimate / Cost estimate.
- Click on: New.
- Select the entry layout..
- Select a project in Project so that you can link the team to this project.
- Click on the action: F5. Select.
- Specify the cost estimate line(s).
- Click on: Finish.
Depending on your settings in the cost estimate entry layout, Profit asks if you want to create a team from this cost estimate. Click on: Yes if this is what you want. Profit adds the specific team.