Release a week for actual costing

Using the Release week action you can release a closed week for an employee. You can then post entries in the period again.

Note: 

Action authorisation applies to the Release week action. The action button is only available for employees for whom the week has been closed as well as those for whom the week has not yet been processed.

To release a week:

  1. Go to:Projects / Actual costing / Actual costing per week.
  2. Select the employee for whom you want to enter the week.
  3. Select a week.

    If you select a closed period, you receive the following message: Period is closed. Choose another period or process this period.

  4. Click on the action: F5. Select.
  5. Click on the action:Release week.
  6. Click on:Cancel to exit the entry window.
  7. Click on: Finish.

Directly to

  1. Actual costing per week
  2. Configure actual costing per week
  3. Enter actual costing per week
  4. Close a week
  5. Release a week
  6. Process weeks
  7. Process weeks in a split week